Elliot Road Waterline - Sossaman to Signal Butte Road

Project Details

Kinkaid Civil Construction has been awarded the project to construct improvements to the water transmission system in the southeast valley. The contractor will construction a new 42-inch waterline along Elliot Road from Signal Butte to Hawes Road. From Hawes Road to Sossaman, the contractor will install a 30-inch waterline. This new waterline will distribute water from the new plant being construction at the northeast corner of Signal Butte and Elliot Road. 

This project is critical to support the City of Mesa planned growth in the southeast Mesa area. The Falcon Field Transmission Main (new waterline) will provide water supply from the Signal Butte Water Treatment Plant that is currently under construction.

Project Schedule/Updates

UPDATE: September, 2017

Construction began the week of March 6, 2016.  Crews are currently installing 42" waterline from Hawes to the east. To date they have installed 7,600 feet of pipe!

Next Up....

To complete the pipe installation near the 202 Freeway, the contractor has shifted all traffic to the south side of Elliot Road. This barricade set-up will remain for approximately three weeks (end of September). The contractor anticipates completing the work between Hawes and Ellsworth Road and the majority of the barricading to be removed in this area by the end of November, 2017. 

 

CAP Raw Water Pipeline Project

Project Details

Garney Construction was awarded the Construction Manager at Risk (CMAR) to install a 54-inch pipeline that will extend along Elliot Road from Signal Butte Road to the east for approximately three miles. This pipeline will ultimately provide up to 53 million gallons of water per day to the Signal Butte Water Treatment Plant.

Project Schedule/Updates

UPDATE: September, 2017 

Garney Construction is really making progress! To date, they have installed almost 11,600 feet of 54” pipe (that’s over two miles of pipe)! The sewer manhole in the intersection of Signal Butte and Elliot Road is also completed.  

NEXT UP…

Over the next several weeks, crews will continue pipe installation east on Elliot Road towards Meridian Road. Mountain Road will be CLOSED south Elliot Road from 9 am on Wednesday, September 20th through 5 am on Friday, September 29th to allow the contractor to install the 54" pipe through the intersection. 

Mountain Road CLOSED South of Elliot Road

Restrictions Elliot Road and Signal Butte Road

Restrictions on Elliot from Signal Butte Road to Meridian

If you have any questions, please contact Rene Powell or Michele Arrollado at 480-644-3800.